Eurofiber reconstruction work - Primary BGP route down from 18-06-2020 22:45 CEST to 19-06-2020 07:00 CEST

Scheduled Maintenance Connectivity Autonomous System AS15966 Datacenter Shared Colocatie Schinnen Network Core Network Inter-Datacenter VLANs PoP Location Equinix AM7 PoP Location Engie
18-06-2020 22:45 CEST · 8 hours, 15 minutes

Update

Update

Dear Customer,

We would like to inform you that the scheduled maintenance activities, known by reference numbers KA-736002, have been completed.
As expected, there was no impact on our network.

When you have any questions about this maintenance, please open a ticket by sending an email to our NOC team at support@emango.nl.

Emango NOC

November 4, 2021 · 16:24 CEST
Scheduled

Dear customer,

Eurofiber will be having a scheduled maintenance on our network soon. This work is necessary to continue guaranteeing the high quality and reliability of their network. They will make sure to minimize the duration of any impact on our connection. These activities have been registered as KA-736002 .

The service window runs from June 18, 2020 - 22:45 local time till June 19, 2020 - 07:00 local time local time. Our local time is CET in the winter and CEST during the summer.

Reconstruction work is carried out by the local/county council. Eurofiber is obliged to physically move a section of their network. We are unable to provide a specific timetable or order of works. Please consider that the interruption may last during the complete service window.

During the maintenance our secondary route should carry all traffic and you might only see some link flapping. No further impact is expected.

When you have any questions about this maintenance, please open a ticket by sending an email to our NOC team at support@emango.nl.

Emango NOC

November 4, 2021 · 16:24 CEST