Equinix Scheduled Outage in 45 minutes: Preventive maintenance low-voltage distribution panel C at AM5 [5-205814599072] from 03-07-2021 22:00 CEST to 04-07-2021 06:00 CEST

Scheduled Maintenance Connectivity Autonomous System AS15966 Datacenter Shared Colocatie Schinnen Network Core Network Inter-Datacenter VLANs PoP Location Equinix AM5
03-07-2021 22:00 CEST · 8 hours

Update

Scheduled

DATE: 03-JUL-2021 - 04-JUL-2021

LOCAL: SATURDAY, 03 JUL 22:00 - SUNDAY, 04 JUL 06:00
UTC: SATURDAY, 03 JUL 20:00 - SUNDAY, 04 JUL 04:00

IBX: EQUINIX AM5

Planned maintenance action: Please be advised that Equinix and their approved contractor will be performing preventive maintenance on its main low-voltage distribution panel C at their data centre.

This maintenance involves switching the primary or redundant power supply(s) to multiple cabinets off for a time frame of 8 hours. After the maintenance is completed the power supply will be switched back on.

During these works, the remaining feed(s) to our cabinets will remain available and ups and generator backed.

Most of our equipment is connected to both power feeds. Single fed equipment is connected to our ATS. This should prevent any outage of our equipment in this POP location.

Duration: eight (8) hours.

Regards,

Emango NOC

November 4, 2021 · 16:25 CEST

← Back