CRAC Maintenance from 2020-01-09 08:30 CET to 2020-01-09 15:00 CET
Scheduled Maintenance
Datacenter
Shared Colocatie Schinnen
Datacenter Utilities
Cooling
2020-01-09 08:30 CET
·
6 hours, 30 minutes
Update
Update
January 9, 2020 · 18:27 CET
The maintenance has been completed successfully.
Scheduled
January 6, 2020 · 22:52 CET
We would like to inform you about an upcoming maintenance window.
Please be advised that our supplier will be performing regular maintenance on our downflow cooling systems.
“Periodic maintenance and control activity on our downflow cooling systems”.
No impact is expected on our services. Cooling capacity will be fully available during the maintenance.
Emango’s Servicedesk is available to provide up-to-date status information or additional details, should you have any questions regarding the maintenance