UPS Maintenance from 2020-02-07 14:00 CET to 2020-02-07 18:00 CET
Scheduled Maintenance
Datacenter Utilities
UPS
2020-02-07 14:00 CET
·
4 hours
Update
Update
February 7, 2020 · 18:05 CET
The maintenance has been completed succesfully.
Update
February 7, 2020 · 14:08 CET
The engineer will start the work at 14:15 hours
Scheduled
February 7, 2020 · 14:07 CET
Dear customer,
We would like to inform you about an upcoming maintenance window.
Please be advised that our supplier Schneider Electric will be performing regular maintenance on our UPS system.
“Maintenance activity to UPS system and battery strings”.
No impact is expected on our services.