Physical move of (public) connections to a new hardware platform from 23-06-2022 23:00 CEST to 24-06-2022 06:00 CEST

Scheduled Maintenance Cloud Virtual Private Cloud Single-Site Schinnen Managed VPS - Windows Managed VPS - Linux Connectivity Autonomous System AS15966 Datacenter Shared Colocatie Schinnen Network Core Network Security Shared Firewall Firewall (Managed) Online Back-up Anti-Virus (Managed) Overige / Shared SMTP Servers Spamfilter Webhosting (Windows) Webhosting (Linux)
23-06-2022 23:00 CEST · 7 hours

Update

Update

Dear customer,

The maintenance has been completed successfully.

Unfortunately we haven’t been able to migrate all ports during this maintenance window. The remaining ports will be completed tomorrow evening.

Emango NOC

June 24, 2022 · 04:37 CEST
Scheduled

Dear customer,

Infrastructure maintenance has been scheduled for this evening starting at 23:00 hours. All public facing interfaces will be migrated to a new hardware platform. This will be done step by step. Due to the physical move of the patches, a short disruptions will occur on your connection. Of course we will keep this downtime as minimal as possible.

Please find below the timeframe for the scheduled works.

Start Date / Start Time (CET): 2022-06-23 - 23:00
End Date / End Time (CET): 2022-06-24 - 06:00

Should you have any questions regarding this maintenance, please feel free to contact Emango @ 088-4435200 or e-mail support@emango.nl.

Emango NOC

June 23, 2022 · 12:02 CEST